Lift and Shift for food plants: Safe, Hygienic, and On Time
Lift and Shift for food plants: safe, hygienic, and on time
Reorganising a line, swapping a filler, or moving a whole cell across the hall – it’s all doable without derailing production. Here’s how we plan and deliver machine moves that protect hygiene, hit windows, and hand back the kit ready for audit.
What a good relocation looks like (in practice)
- End-to-end delivery, including disconnection, move, reinstatement, and recommissioning, handled by a single team (mechanical, electrical, and controls).
- Hygiene-first – zoned PPE/gowning, temporary containment, HEPA where needed, validated clean-downs.
- Compliant lifting/isolations – RAMS and lift plans; PUWER/LOLER kit and supervision; CDM 2015 where thresholds apply.
- On your clock – weekends, overnights, low-volume shifts, and shutdowns with multi-crew options for parallel moves.
Related services: Mechanical & Electrical and Industrial Project Management. Expert Mechanical and Electrical Services by FESS Group
The simple plan we use most weeks
- Survey and scope
Space checks, services, access routes, weight/centre-of-gravity, hygiene constraints. - Paperwork that stands up
RAMS, lifting plans, permits, isolations, and disconnection marks. Hygiene and safety packs aligned to site rules. - Lift and Shift
Skates, gantries, forklifts or cranes; stainless fixings and sealed conduits where required. Controlled mechanical/electrical disconnection and re-fit. - Re-establish & validate
Alignment and levelling; utilities re-tie; electrical continuity/insulation/I-O; motor/drive tests; functional checks and production sign-off. As-built docs updated.
High-care moves: hygiene controls that actually work
- Zoned PPE and gowning
- Temporary barriers and HEPA air control (as needed)
- Chemical-resistant cabling and sealed containment
- Tool/waste segregation and validated pre-/post-clean
All delivered to site standards and customer audit expectations (BRCGS/IFS).
Scheduling without stopping output
- Weekend/overnight installs
- Phased works during low-volume shifts
- “Temporary keeps-you-running” utilities where sensible
- Multi-crew setups for parallel assets
We plan with production, hygiene, and engineering to ensure that changeovers don’t steal capacity.
Lifting and handling – by the book
Skates, gantries, jacks, forklifts and cranes as the job demands – all kit certified, all lifts risk-assessed and supervised. PUWER/LOLER compliance. CDM 2015 applied when thresholds are met (we can act as Principal Contractor).
Common traps – and how to dodge them
- Trap: “We’ll sort it all in the shutdown.”
Better: Pre-stage disconnections and off-line prep so shutdowns are for reinstatement and validation only. - Trap: Splitting trades across three contractors.
Better: One joined-up M&E/controls team to cut handover risk and speed fault-finding. - Trap: Hygiene as an afterthought.
Better: Include containment, gowning, and validated cleaning in the RAMS, not the toolbox chat.
Timings, budgets, and seasonality (so you can plan)
- Typical duration: single-machine moves in 1–2 shifts; full-line moves 2–5 days with phased install.
- Typical budgets: full-line relocations often start £5k–£20k+, depending on hygiene scope and M&E complexity.
- Q4 peak: book 6–8 weeks ahead where possible; we hold limited emergency slots.
Handover you can trust
You’ll receive mechanical safety checks, electrical test results (including continuity, IR, and I/O), motor/drive tests, functional sign-off, and updated as-builts; all ready for audit.
Why FESS?
- End-to-end, one team – mechanical, electrical, automation in-house.
- Food-sector experience – high-care methods as standard.
- Certified and available – SafeContractor, ECA, IOSH; 24/7 rapid response.
- On time and on budget – with UK-wide mobilisation. Contact FESS Group – We’re Here to Help.
See similar projects on our Case Studies hub. Case Studies Archive – FESS Group
FAQs
How long does a typical lift and shift move take?
Single assets: 1–2 shifts. Full lines: 2–5 days with phased install.
Can you work without stopping production?
Yes, we plan around nights, weekends and low-volume windows and use temporary utilities where needed.
What does “audit-ready” mean in practice?
Documented tests, alarm/IO checks where relevant, and as-built drawings to support site audits.
Does CDM 2015 apply to high-care moves?
Yes, if thresholds are met (e.g. duration or multi-contractor work). We can act as the Principal Contractor and manage documentation.
How soon should we book Q4 works?
6–8 weeks ahead is sensible; we’ll advise on capacity and staging.
Next steps
- Plan your move: speak to our project team. Contact FESS Group – We’re Here to Help
- Explore services that often pair with Lift and Shift: M&E installation, Industrial Project Management. Expert Mechanical and Electrical Services by FESS Group, Industrial Project Management & Expert Consultancy
- See how we deliver under pressure: browse Case Studies. Case Studies Archive – FESS Group